Raft River to go online Q407


Construction photo of Raft River geothermal plant in Idaho

In an update today, US Geothermal reports major progress on the 13MW Unit 1 plant at Raft River, Idaho:

  • All major power plant equipment has been delivered to site and set on foundations.
  • The prime electrical construction contract was awarded to Merit Electric Incorporated in May.
  • Piping and electrical connections are proceeding on schedule.
  • The control room and motor control center building has been erected and switchgear installed.
  • The cooling tower is 95% complete.
  • The geothermal injection pumps and motors have been set in place.
  • High voltage interconnection to BPA substation with Idaho Power and Raft River Electrical Co-operative metering is nearing completion.
  • The cooling water supply piping system is approximately 75% complete for initial operations.