Raft River to go online Q407
In an update today, US Geothermal reports major progress on the 13MW Unit 1 plant at Raft River, Idaho:
- All major power plant equipment has been delivered to site and set on foundations.
- The prime electrical construction contract was awarded to Merit Electric Incorporated in May.
- Piping and electrical connections are proceeding on schedule.
- The control room and motor control center building has been erected and switchgear installed.
- The cooling tower is 95% complete.
- The geothermal injection pumps and motors have been set in place.
- High voltage interconnection to BPA substation with Idaho Power and Raft River Electrical Co-operative metering is nearing completion.
- The cooling water supply piping system is approximately 75% complete for initial operations.